SSC CGL Quant – Time & Work, Pipes & Cisterns – Tier II Level · Marathon

← Back

SSC CGL Quant – Time & Work, Pipes & Cisterns – Tier II Level · Marathon – 10 questions, subject: Quantitative Aptitude. Every question has the correct answer with a two-line explanation; tap "Show Answer". Free practice for TNPSC, UPSC, SSC, Bank and RRB exams – Shanmugam IAS Academy, Coimbatore.

Get daily current affairs & exam alerts – follow us YouTube WhatsApp Channel Telegram Channel Facebook Page Instagram
Share with friends & study groups
Link to this page from your website / blog (HTML code)
1.  
A can do a work in 9 days and B in 12 days. They work on alternate days, A starting. In how many days is the work finished?

Correct Answer: B [10¼ days]

Explanation:

Taking total work 36 units, A does 4 and B 3 units a day, so 5 two-day cycles (10 days) complete 35 units. On day 11 A does the last 1 unit in 1/4 day, so the work ends in 10¼ days.

2.  
In the previous situation (A 9 days, B 12 days, alternate days), if B starts instead, the work is finished in:

Correct Answer: C [10⅓ days]

Explanation:

Taking total work 36 units, A does 4 and B 3 units a day, so every two days give 7 units and 10 days give 35 units. On day 11 it is B's turn, and B does the last 1 unit in 1/3 day, so the work ends in 10⅓ days.

3.  
Pipes A and B can fill a tank in 6 hours and 4 hours. They are opened alternately for 1 hour each, A first. In how many hours is the tank full?

Correct Answer: A [5 hours]

Explanation:

Taking the tank as 12 units, A fills 2 units an hour and B 3 units, so each 2-hour cycle fills 5 units. After 2 cycles (4 hours) 10 units are filled, and in the 5th hour A adds the last 2 units, so the tank is full in exactly 5 hours.

4.  
A can do a work in 20 days and B in 30 days. A starts the work and B joins him after 5 days. In how many days in all is the work finished?

Correct Answer: D [14 days]

Explanation:

Taking total work 60 units, A does 3 units a day and B 2, so in the first 5 days A alone does 15 units. The remaining 45 units at 5 units a day take 9 days, so the work is finished in 5 + 9 = 14 days.

5.  
A, B and C can do a job in 9, 12 and 36 days. They start together, but C leaves 4 days before the work is finished. In how many days is the work finished?

Correct Answer: D [5 days]

Explanation:

Taking total work 36 units, A, B and C do 4, 3 and 1 units a day. If the work takes D days, A and B work all D days and C works D − 4 days: 7D + (D − 4) = 36 gives D = 5 days.

6.  
A can do a job in 24 days. After working 6 days at his normal rate, he increases his efficiency by 50%. In how many days in all does he finish?

Correct Answer: A [18 days]

Explanation:

Take the job as 24 units, so A does 1 unit a day and finishes 6 units in the first 6 days. The remaining 18 units at 1.5 units a day take 12 days, so the job is finished in 6 + 12 = 18 days.

7.  
10 men working 6 hours a day dig a 240 m trench in 12 days. In how many days will 15 men working 8 hours a day dig a 400 m trench?

Correct Answer: C [10 days]

Explanation:

Work per metre is (10 × 6 × 12) ÷ 240 = 3 man-hours, so a 400 m trench needs 1,200 man-hours. With 15 men × 8 hours = 120 man-hours a day, it takes 1,200 ÷ 120 = 10 days.

8.  
Statement-basedWhich of the following is/are correct?
I. If A and B together take T days, each of them alone takes more than T days.
II. If A and B each take 10 days alone, working on alternate days they finish in 10 days.
III. A leak that makes a pipe of a hours take b hours empties a full tank in ab/(b − a) hours.

Correct Answer: B [All three]

Explanation:

I: rates are positive. II: each day does 1/10 → 10 days.

9.  
A and B can do a job in 10 and 15 days and are paid ₹ 6,000 for it. They start together; A leaves after 3 days and B finishes. What is A's share?

Correct Answer: D [₹ 1,800]

Explanation:

LCM 30: A 3, B 2. A worked 3 days = 9 units of 30 → 9/30 × 6,000 = 1,800.

10.  
A pipe fills a tank in 4 hours. When the tank is half full, a leak develops and the rest of the filling takes 1 hour more than usual. In how many hours can the leak alone empty a full tank?

Correct Answer: B [12 hours]

Explanation:

Normally the second half takes 2 h; it took 3 h → net 1/6 per hour.

➤ Full notes, shortcuts and every answer explained – SSC CGL 2026 Quantitative Aptitude book (₹149): www.shanmugamiasacademy.in/study-materials/ssc-cgl-quantitative-aptitude

📘 SSC CGL 2026 – Quantitative Aptitude (Tier I + Tier II)
Here you get the answer with a one-line explanation. 1,052 original questions with answer key and explanations · mind-maps, notes, tables and shortcuts · Tier I and Tier II practice sets + 3 mock tests
Get the book – ₹149 ₹299 →
Score: 0 Answered: 0 / 0