UPSC CSAT Numeracy – Chapter 13: Time and Work (38 MCQs)
UPSC CSAT Numeracy – Chapter 13: Time and Work (38 MCQs) – 38 questions, subject: CSAT Numeracy. Every question has the correct answer with a two-line explanation; tap "Show Answer". Free practice for TNPSC, UPSC, SSC, Bank and RRB exams – Shanmugam IAS Academy, Coimbatore.
Link to this page from your website / blog (HTML code)
Correct Answer: A [4 days]
Explanation:
Take the job as 60 units (LCM of 10, 12 and 15); A, B and C do 6 + 5 + 4 = 15 units a day, so they finish in 60 ÷ 15 = 4 days. Working together they must be faster than the fastest worker alone (10 days), so only 4 days fits.
Correct Answer: B [8 days]
Explanation:
Man-days are fixed: 10 × 12 = 120 man-days, so 15 men need 120 ÷ 15 = 8 days. More men means fewer days, so the answer must be below 12, which rules out 18 days.
Correct Answer: C [1/8 of the job]
Explanation:
A worker who finishes a job in 8 days at a steady rate does 1/8 of the job each day. In general, if a job takes n days, the daily rate is 1/n, and rates of different workers can be added.
Correct Answer: D [12 days]
Explanation:
Total work in man-hours is fixed: 12 × 8 × 15 = 1,440 = 20 × 6 × D, so D = 1,440 ÷ 120 = 12 days. More men speed the job up but fewer hours a day slow it, so both changes must be applied together.
Correct Answer: B [37.5 days]
Explanation:
The total store (daily use × days) is fixed, so cutting daily use to 80 per cent makes it last 30 × 100/80 = 37.5 days. Adding 20 per cent to 30 days (36 days) is the tempting error, because a 20 per cent cut in use means a 25 per cent rise in days.
Correct Answer: B [₹4,500]
Explanation:
A's rate is 1/8 and B's is 1/24 of the job a day, a ratio of 3 : 1, so A gets 3/4 of ₹6,000 = ₹4,500. Wages for a shared job are always divided in the ratio of the work each person does.
Correct Answer: C [40 days]
Explanation:
If one-fourth of the job takes 10 days, the whole job at the same rate takes 10 × 4 = 40 days (that is, 10 ÷ 1/4). Multiplying 10 by 1/4 instead gives 2.5 days, which is the tempting wrong option.
Correct Answer: D [48 units]
Explanation:
48 is the LCM of 8, 16 and 12, the smallest number of units divisible by all three. The daily rates then become whole numbers: 48/8 = 6, 48/16 = 3 and 48/12 = 4 units.
Correct Answer: A [₹1,360]
Explanation:
The penalties form an arithmetic series 100, 120, …, with the 8th day costing 100 + 7 × 20 = ₹240. The total is 8/2 × (100 + 240) = ₹1,360.
Correct Answer: B [1 and 3 only]
Explanation:
When people work together their rates add, and with equally efficient workers the man-days for a fixed job stay constant (M₁D₁ = M₂D₂), so statements 1 and 3 are correct. Statement 2 is wrong because times do not add; working together shortens the time.
Correct Answer: A [Both A and R are true, and R is the correct explanation of A]
Explanation:
Since 4 men = 6 women in work, one man equals 1.5 women, so 3 women do the work of 2 men. The team of 2 men and 3 women equals 4 men, who take 12 days, so R explains A.
Correct Answer: C [5]
Explanation:
Together they do 1/15 + 1/10 = 1/6 of the job a day, so in 3 days they finish half. B alone (1/10 a day) needs 5 more days for the other half.
Correct Answer: D [24 minutes]
Explanation:
In the first 8 minutes both pipes fill 8/24 + 8/36 = 1/3 + 2/9 = 5/9 of the tank. B fills the remaining 4/9 in 4/9 × 36 = 16 minutes, so 8 + 16 = 24 minutes in all.
Correct Answer: D [18 days]
Explanation:
In 5 days A does 5/15 = 1/3 of the job, so B does the remaining 2/3 in 12 days. B alone would take 12 ÷ (2/3) = 18 days.
Correct Answer: C [16 days]
Explanation:
A does 1/20 of the job a day, and B, 25% more efficient, does 1.25 × 1/20 = 1/16 a day. So B alone needs 16 days, not 15 (which would be 25% less time).
Correct Answer: B [3-1-4-2]
Explanation:
A and B together take 1 ÷ (1/6 + 1/12) = 4 days, and B and C together take 1 ÷ (1/12 + 1/24) = 8 days, while A alone takes 6 and B alone 12. In increasing order 4, 6, 8, 12 gives 3-1-4-2.
Correct Answer: D [30 hours]
Explanation:
The net filling rate is 1/10 − 1/15 = 3/30 − 2/30 = 1/30 of the tank per hour. So with the leak open, the tank fills in 30 hours.
Correct Answer: A [7/24 of the job]
Explanation:
X does 1/6 of the job in one hour and Y does 1/8 in one hour. Together the two hours complete 1/6 + 1/8 = 4/24 + 3/24 = 7/24 of the job.
Correct Answer: B [10 days]
Explanation:
The wall needs 20 × 12 = 240 man-days, and 20 × 4 = 80 are done in 4 days, leaving 160. The remaining 16 men need 160 ÷ 16 = 10 days.
Correct Answer: A [8 days]
Explanation:
Together they do 1/12 + 1/24 = 3/24 = 1/8 of the job per day. Hence they finish the job in 8 days.
Correct Answer: B [12 minutes]
Explanation:
Together the pipes fill 1/20 + 1/30 = 5/60 = 1/12 of the tank per minute. So they fill the tank completely in 12 minutes, which is the product over sum 20 × 30 ÷ 50.
Correct Answer: D [Z]
Explanation:
The full-work times are W = 30 × 4 = 120 days, X = 10 × 4 = 40 days, Y = 40 × 2.5 = 100 days and Z = 13 × 3 = 39 days. So Z, at 39 days, finishes first, just ahead of X at 40 days.
Correct Answer: A [6]
Explanation:
X does 20% in 8 days, so the whole in 40 days; Y does 25% in 6 days, so the whole in 24 days. Together they do 1/40 + 1/24 = 1/15 a day, so 40% takes 0.4 × 15 = 6 days.
Correct Answer: D [15]
Explanation:
7/8 of the job takes 21 days, so the full job takes 24 days, and 1.5 times the job takes 36 days. He needs 36 − 21 = 15 more days.
Correct Answer: C [20%]
Explanation:
Men and days are inversely proportional for the same work, so the men needed change in the ratio 6k : 5k = 6 : 5. The increase is 1/5 of the original number, that is 20%.
Correct Answer: D [10 days]
Explanation:
After 10 days, the food left would last 1,000 soldiers for 20 more days, that is 20,000 soldier-days. With 2,000 soldiers it lasts 20,000 ÷ 2,000 = 10 days.
Correct Answer: D [8]
Explanation:
Using 25% more each day means 1.25 times the daily use, so the same tank lasts 10 ÷ 1.25 days. That equals 8 days, since time is inversely proportional to the rate of use.
Correct Answer: C [20]
Explanation:
With 5% unfit, the saleable output is 95% of 1000 = 950 units per day. Days needed = 19,000 ÷ 950 = 20 days.
Correct Answer: D [Data is inadequate to draw any conclusion]
Explanation:
The total work is 24M + 12W per day for 30 days, but the efficiency of a man compared with a woman is not given. Without that ratio the time for 12 men and 24 women cannot be found, so the data is inadequate.
Correct Answer: C [10 days]
Explanation:
Together they do 60% in 4 days, that is 15% a day; Shyam alone does the remaining 40% in 8 days, that is 5% a day. Ram's rate is 15% − 5% = 10% a day, so he needs 10 days alone.
Correct Answer: A [3:1:1]
Explanation:
P = 3Q in rate, and P + Q = 4Q = 4R, so R = Q. Earnings are shared in the ratio of work rates, 3 : 1 : 1.
Correct Answer: A [1 only]
Explanation:
Taking the work as 48 units (LCM of 8, 16, 12), A, B and C do 6, 3 and 4 units a day, so each three-day cycle gives 13 units and 9 days give 39 units. Day 10 (A) brings it to 45 and day 11 (B) to 48, so the work ends on the 11th day, which is a Thursday; statement 1 is correct and statement 2 is wrong.
Correct Answer: C [6 hours 45 minutes]
Explanation:
X (1/6 per hour) cannot work two hours in a row, so the best order is X, Y, X, Z, X, Y, which does 3/6 + 3/8 = 7/8 of the work in 6 hours. X then does the last 1/8 in (1/8) ÷ (1/6) = 3/4 hour = 45 minutes, giving 6 hours 45 minutes.
Correct Answer: B [Rs. 4250]
Explanation:
The daily penalties form an arithmetic progression 200, 250, 300, ..., so the 10th day's penalty is 200 + 9 × 50 = Rs. 650. Total = 10/2 × (200 + 650) = 5 × 850 = Rs. 4,250.
Correct Answer: A [48 minutes]
Explanation:
From 11:00 am to 2:27 pm is 207 minutes, and the three rests between the four periods take 15 minutes. Each period is (207 − 15) ÷ 4 = 48 minutes; no rest is counted after the last period.
Correct Answer: A [23 minutes]
Explanation:
Under the given rules: A and B cross (2), A returns (1), A and C cross (7), A returns (1), A and D cross (10), then A brings the lamp back (1) and crosses without it (1). The total is 2 + 1 + 7 + 1 + 10 + 1 + 1 = 23 minutes.
Correct Answer: D [16 minutes]
Explanation:
Per pipe per minute: X fills 0.7 ÷ (20 × 14) = 1/400; Y fills 3/8 ÷ (10 × 6) = 1/160; Z empties 1/2 ÷ (16 × 20) = 1/640. Open now: 10 X, 5 Y, 16 Z, so the net rate is 10/400 + 5/160 − 16/640 = 1/40 + 1/32 − 1/40 = 1/32 of the tank a minute. Half the tank takes 16 minutes.
Correct Answer: B [4]
Explanation:
X alone takes 18 days, Y 24 and Z 16 (three-fourths in 12). Together they do 1/18 + 1/24 + 1/16 = (8 + 6 + 9)/144 = 23/144 a day. Y alone in 26/3 days does 26/3 × 1/24 = 52/144. The rest, 92/144, took n days at 23/144 a day, so n = 4.
➤ Class X level methods, shortcuts with proof, worked solutions to UPSC CSAT numeracy PYQs and a reason for every option – U25 · CSAT Numeracy (UPSC book, ₹249): www.shanmugamiasacademy.in/study-materials/upsc-csat-numeracy
Today Current Affairs in Tamil | 23 நவம்பர் 2026 | TNPSC Group 4 முக்கிய வினாக்கள்
📚 UPSC Civil Services Books (Prelims & Mains)
PDF நூல்கள் · ₹149 முதல் · ஒவ்வொன்றுக்கும் 50 பக்க இலவச மாதிரி · UPI-இல் பணம் செலுத்தியதும் உடனே பதிவிறக்கம்
U27 · CSAT Mock Tests with Analysis – UPSC Civil Services (Prelims Paper II – CSAT)
₹249
U11 · Indian Polity & Constitution – UPSC Civil Services (Prelims & Mains)
₹249
U03 · Modern Indian History – UPSC Civil Services (Prelims & Mains)
₹249
U15 · Indian Economy – UPSC Civil Services (Prelims & Mains)
₹249TNPSC குரூப் 1, 2/2A, 4 – நேரடி வகுப்புகள் · கோவை & மதுரை
2006 முதல் சண்முகம் IAS அகாடமி · Classroom & online coaching in Coimbatore and Madurai