IBPS Clerk Quant – Time & Work, Pipes & Cisterns – Level 2 · Exam Level · Prelims Level – 15 questions, subject: Quantitative Aptitude. Every question has the correct answer with a two-line explanation; tap "Show Answer". Free practice for IBPS Clerk, IBPS PO, SBI, RRB exams – Shanmugam IAS Academy, Coimbatore.

Get daily current affairs & exam alerts – follow us YouTube WhatsApp Channel Telegram Channel Facebook Page Instagram
Share with friends & study groups
Link to this page from your website / blog (HTML code)
1.  
A, B and C can do a job in 20, 30 and 60 days respectively. Working together, they finish it in:

Correct Answer: A [10 days]

Explanation:

With the job as 60 units, A, B and C do 3, 2 and 1 units per day. Together they do 6 units/day, so the job takes 60 ÷ 6 = 10 days.

2.  
A and B can do a job in 8 days, B and C in 12 days, and C and A in 24 days. In how many days can A, B and C together do it?

Correct Answer: E [8 days]

Explanation:

With the job as 24 units, A + B = 3, B + C = 2 and C + A = 1 unit/day, so 2(A + B + C) = 6. Hence A + B + C = 3 units/day and they finish in 24 ÷ 3 = 8 days.

3.  
15 men working 8 hours a day lay 1.2 km of road in 16 days. In how many days will 20 men working 6 hours a day lay 1.5 km?

Correct Answer: B [20 days]

Explanation:

Using M₁D₁H₁/W₁ = M₂D₂H₂/W₂: 15 × 16 × 8/1.2 = 20 × D × 6/1.5. So D = 15 × 16 × 8 × 1.5/(1.2 × 20 × 6) = 2,880/144 = 20 days.

4.  
A is 60% more efficient than B. Together they finish a job in 20 days. How many days will B alone take?

Correct Answer: C [52 days]

Explanation:

If B = 5 units/day, A (60% more) = 8, so the job = (8 + 5) × 20 = 260 units. B alone needs 260 ÷ 5 = 52 days.

5.  
A can do a job in 12 days and B in 18 days. They do it together and receive ₹ 6,000. A's share is:

Correct Answer: D [₹ 3,600]

Explanation:

With the job as 36 units, A does 3 and B 2 units per day, so the money is shared 3 : 2. A gets 3/5 × ₹ 6,000 = ₹ 3,600 and B gets ₹ 2,400.

6.  
A pipe can fill a tank in 6 hours. Because of a leak it takes 8 hours. The leak alone can empty the full tank in:

Correct Answer: C [24 hours]

Explanation:

Leak rate = 1/6 − 1/8 = 1/24 of the tank per hour, so the leak alone empties it in 24 hours. Shortcut: xy/(y − x) = 6 × 8/2 = 24.

7.  
A can finish a job in 20 days. He works alone for 5 days, and then B, who can finish the job alone in 30 days, joins him. In how many days in all is the job finished?

Correct Answer: E [14 days]

Explanation:

LCM 60: A 3, B 2. 5 days → 15 units; 45 ÷ 5 = 9 more days → 14 days.

8.  
A can do a job in 6 days and B in 9 days. They work on alternate days with A starting. The job is finished in:

Correct Answer: A [7 days]

Explanation:

With the job as 18 units, A does 3 and B 2 units per day, so every 2-day cycle does 5 units and 3 cycles do 15 units in 6 days. On day 7 A does the last 3 units, so the job ends in exactly 7 days.

9.  
Quantity I: Days taken by 6 men to finish a job that 9 men finish in 14 days.
Quantity II: Days taken by A and B together, if A alone needs 30 days and B alone 70 days.

Correct Answer: E [Quantity I = Quantity II or relation cannot be established]

Explanation:

I: 9 × 14/6 = 21. II: 30 × 70/100 = 21.

10.  
In how many days can B alone finish the job?
I. A and B together finish it in 8 days.
II. A is twice as efficient as B.

Correct Answer: D [Both statements together are needed]

Explanation:

From II, A : B efficiency = 2 : 1, and from I the job = (2 + 1) × 8 = 24 units, so B alone takes 24 ÷ 1 = 24 days. Statement I gives only the combined time and II only the ratio, so both are needed.

11.  
Trick Spotter: A alone takes 18 days and A and B together take 12 days. Which is the fastest correct way to find B's time alone?

Correct Answer: C [18 × 12/(18 − 12)]

Explanation:

B's rate = 1/12 − 1/18 = (18 − 12)/(18 × 12), so B alone takes 18 × 12/(18 − 12) = 216/6 = 36 days. Option b, the product over the sum, gives the combined time of two workers, not the missing one.

12.  
Pipe A fills a tank in 4 hours; pipe B empties it in 6 hours. Which of the following is/are correct?
I. If both are opened in the empty tank, it fills in 12 hours.
II. With both open, 1/10 of the tank fills in 1 hour.
III. If both are open for 6 hours and then B is closed, A fills the rest in 2 hours.

Correct Answer: C [Only I and III]

Explanation:

The net filling rate is 1/4 − 1/6 = 1/12 per hour, so I is true and II (1/10) is false. After 6 hours half the tank is full, and A alone fills the other half in 4 × 1/2 = 2 hours, so III is true.

13.  
2 men or 3 women can finish a job in 24 days. In how many days will 4 men and 3 women finish it together?

Correct Answer: B [8 days]

Explanation:

Since 2 men = 3 women, one woman = 2/3 man, so 4 men + 3 women = 4 + 2 = 6 men. The job is 2 × 24 = 48 man-days, so 6 men finish it in 48 ÷ 6 = 8 days.

14.  
Reverse question: A and B together finish a job in 6 days, and A alone takes 5 days less than B alone. How many days does A alone take?

Correct Answer: C [10]

Explanation:

If A takes 10 days, B takes 15 days and together they take 10 × 15/(10 + 15) = 150/25 = 6 days, as required. Algebraically, 1/x + 1/(x + 5) = 1/6 gives x² − 7x − 30 = 0, so x = 10.

15.  
Three pipes A, B and C can fill a tank in 10, 12 and 15 hours respectively. If all three are opened together, the tank fills in:

Correct Answer: D [4 hours]

Explanation:

With the tank as 60 units, A, B and C fill 6, 5 and 4 units per hour. Together they fill 15 units/h, so the tank is full in 60 ÷ 15 = 4 hours.