IBPS Clerk Quant – Time & Work, Pipes & Cisterns – Mains Level · Efficiency chains, Quantity comparison, Data sufficiency
IBPS Clerk Quant – Time & Work, Pipes & Cisterns – Mains Level · Efficiency chains, Quantity comparison, Data sufficiency – 11 questions, subject: Quantitative Aptitude. Every question has the correct answer with a two-line explanation; tap "Show Answer". Free practice for IBPS Clerk, IBPS PO, SBI, RRB exams – Shanmugam IAS Academy, Coimbatore.
Link to this page from your website / blog (HTML code)
Directions (Q 36–39): A municipal office in Tiruppur gives a record-scanning job to three clerks. A alone can finish the job in 36 days. B is 20% more efficient than A, and C is 20% less efficient than A.
Correct Answer: D [30 days]
Explanation:
If A = 5 units/day, B (20% more efficient) = 6 and C (20% less) = 4, and the job = 5 × 36 = 180 units. B alone needs 180 ÷ 6 = 30 days.
All three start together. After 6 days B is moved to another job, and A and C finish the rest. In how many days in all is the job finished?
Correct Answer: E [16 days]
Explanation:
Here A takes 36 days, B is 20% more efficient and C 20% less, giving 5, 6 and 4 units/day and a 180-unit job. In 6 days all three do 15 × 6 = 90 units, and A and C finish the other 90 units in 90 ÷ 9 = 10 days, so the job takes 6 + 10 = 16 days.
If all three work together for the whole job and are paid ₹ 30,000, C's share is:
Correct Answer: B [₹ 8,000]
Explanation:
Here A takes 36 days, B is 20% more efficient and C 20% less, so their efficiencies are 5 : 6 : 4. Working together for the whole job, wages are shared in that ratio, so C gets 4/15 × ₹ 30,000 = ₹ 8,000.
B works alone for some days; then A and C together finish the remaining job in 8 days. For how many days did B work?
Correct Answer: A [18 days]
Explanation:
Here A takes 36 days, B is 20% more efficient and C 20% less, so with A = 5 units/day, B = 6 and C = 4, and the job = 5 × 36 = 180 units. A and C do 9 × 8 = 72 units in 8 days, so B did 180 − 72 = 108 units in 108 ÷ 6 = 18 days.
Quantity II: Days 18 women need for a job that 12 women finish in 12 days.
Correct Answer: A [Quantity I > Quantity II]
Explanation:
Quantity I: with the tank as 36 units, P fills 3, Q fills 2 and the leak removes 1 unit/h, a net 4 units/h, so 36 ÷ 4 = 9 hours. Quantity II: 12 × 12 = 144 woman-days ÷ 18 = 8 days, so Quantity I > Quantity II.
Quantity I: Days A alone takes.
Quantity II: 30
Correct Answer: C [Quantity I ≥ Quantity II]
Explanation:
If the faster one takes x days, x(x + 30)/(2x + 30) = 20 gives x² − 10x − 600 = 0, so x = 30 and the other takes 60 days. A may be either worker, so A's time is 30 or 60 days, which means Quantity I ≥ Quantity II.
I. Inlets A and B alone fill the tank in 10 h and 15 h respectively.
II. With A, B and C all open, the empty tank fills in 12 h.
Correct Answer: D [Both statements together are needed]
Explanation:
From I, A and B fill 1/10 + 1/15 = 1/6 of the tank per hour; with II, 1/6 − 1/C = 1/12, so 1/C = 1/12 and C empties the tank in 12 hours. Neither statement alone gives C's rate, so both are needed.
I. A and B together finish it in 12 days, and B is 25% less efficient than A.
II. B alone takes 28 days.
Correct Answer: A [Statement I alone is sufficient]
Explanation:
From I, A : B efficiency = 4 : 3, so the job = (4 + 3) × 12 = 84 units and A alone takes 84 ÷ 4 = 21 days. Statement II gives only B's time with no link to A, so I alone is sufficient.
I. 6 men and 4 women finish it in 12 days.
II. 5 men finish it in 24 days.
Correct Answer: B [Statement II alone is sufficient]
Explanation:
Statement II gives 5 × 24 = 120 man-days, so 10 men need 120 ÷ 10 = 12 days. Statement I mixes men and women with no link between their rates, so it alone cannot give the answer.
Correct Answer: E [52 days]
Explanation:
Let R = 5 units/day; Q is 40% more = 7 and P is twice Q = 14, so together they do 26 units/day and the job is 26 × 10 = 260 units. R alone needs 260 ÷ 5 = 52 days.
Correct Answer: D [12 hours]
Explanation:
Take the tank as 30 units: A fills 3 units/h and B 2 units/h, so each 2-hour cycle (A then B) adds 5 units, and 5 cycles = 25 units in 10 h. In hour 11 A brings it to 28 units and in hour 12 B completes 30, so the tank is full in 12 hours.
நடப்பு நிகழ்வுகள் 24 நவம்பர் 2026 | Today Current Affairs in Tamil | TNPSC Group 4 வினா விடை
📚 IBPS Clerk 2026 Books
PDF நூல்கள் · ₹149 முதல் · ஒவ்வொன்றுக்கும் 50 பக்க இலவச மாதிரி · UPI-இல் பணம் செலுத்தியதும் உடனே பதிவிறக்கம்
IBPS Clerk 2026 – Complete Set (5 Books, Prelims + Mains)
₹599
IBPS Clerk 2026 – Quantitative Aptitude (Prelims + Mains)
₹149
IBPS Clerk 2026 – Reasoning Ability (Prelims + Mains)
₹149
IBPS Clerk 2026 – English Language (Prelims + Mains)
₹149TNPSC குரூப் 1, 2/2A, 4 – நேரடி வகுப்புகள் · கோவை & மதுரை
2006 முதல் சண்முகம் IAS அகாடமி · Classroom & online coaching in Coimbatore and Madurai