UPSC Environment and Ecology – Chapter 16: Environmental Impact Assessment (25 MCQs)
UPSC Environment and Ecology – Chapter 16: Environmental Impact Assessment (25 MCQs) – 25 questions, subject: Environment. Every question has the correct answer with a two-line explanation; tap "Show Answer". Free practice for TNPSC, UPSC, SSC, Bank and RRB exams – Shanmugam IAS Academy, Coimbatore.
Link to this page from your website / blog (HTML code)
Correct Answer: A [National Environmental Policy Act, 1969 of the USA]
Explanation:
The US National Environmental Policy Act (NEPA), 1969 was the first law to make environmental impact assessment a legal requirement, through environmental impact statements for major federal actions. The Stockholm (1972) and Rio (1992) Declarations came later and are not binding laws.
Correct Answer: B [2006]
Explanation:
India's current EIA Notification was issued on 14 September 2006 and, as amended many times, remains in force. It replaced the first EIA Notification of 1994; the 2020 version was only a draft and was not finalised.
Correct Answer: C [Environment (Protection) Act, 1986]
Explanation:
The EIA Notification is issued by the Central Government under the Environment (Protection) Act, 1986, using its powers under Section 3 of the Act and Rule 5 of the Environment (Protection) Rules, 1986. The Act is an umbrella law that lets the Centre take all measures needed to protect the environment.
Correct Answer: A [State Environment Impact Assessment Authority]
Explanation:
Under the EIA Notification, 2006, Category B projects are appraised by the State Expert Appraisal Committee (SEAC) and receive environmental clearance from the State Environment Impact Assessment Authority (SEIAA). Category A projects are cleared by MoEFCC at the Centre.
Correct Answer: B [scoping]
Explanation:
At the scoping stage, the Expert Appraisal Committee (EAC) or State Expert Appraisal Committee (SEAC) fixes the Terms of Reference (ToR) that list everything the EIA study must cover. The four stages under the 2006 Notification are screening, scoping, public consultation and appraisal.
Correct Answer: D [State Pollution Control Board]
Explanation:
Under the EIA Notification, 2006, public hearings are conducted by the State Pollution Control Board (or the UT Pollution Control Committee) at or near the project site. The hearing is supervised and presided over by the District Magistrate or Collector (or an officer not below the rank of Additional District Magistrate).
Correct Answer: A [Category B2]
Explanation:
Under the EIA Notification, 2006, Category B2 projects do not need to prepare an EIA report or hold public consultation. Category B1 projects, in contrast, need a full EIA report and public hearing, and the State Expert Appraisal Committee decides the B1 or B2 classification during screening.
Correct Answer: D [45 days]
Explanation:
Under Appendix IV of the EIA Notification, 2006, the public hearing must be completed within 45 days of the request letter from the applicant. If the State Pollution Control Board fails to hold it in time, the regulatory authority can get another agency to conduct it.
Correct Answer: B [an online single window for environment, forest, wildlife and CRZ clearances]
Explanation:
PARIVESH (Pro-Active and Responsive facilitation by Interactive, Virtuous and Environmental Single-window Hub), launched by MoEFCC in 2018, is the online single window for environment, forest, wildlife and CRZ clearances. It allows project proposals to be submitted and tracked online at central, State and district levels.
Correct Answer: C [strategic environmental assessment]
Explanation:
Strategic environmental assessment (SEA) studies the environmental effects of policies, plans and programmes at an early stage, before individual projects are proposed. A project EIA, by contrast, assesses one specific project after it is designed.
Correct Answer: A [Both A and R are true, and R is the correct explanation of A]
Explanation:
Both A and R are true, and R explains A: several hydropower projects on one river can together alter flows, sediment and fish movement far more than any single project. That is why cumulative impact assessment of the whole river basin is needed, not just separate project-wise EIAs.
Correct Answer: D [NABET of the Quality Council of India]
Explanation:
MoEFCC allows only consultants accredited by the National Accreditation Board for Education and Training (NABET) of the Quality Council of India (QCI) to prepare EIA reports. Accreditation is meant to ensure that EIA studies meet minimum standards of competence and quality.
Correct Answer: D [20 days]
Explanation:
The Draft EIA Notification, 2020 proposed cutting the minimum notice period for public hearings from 30 days to 20 days. Critics argued this would make it harder for affected communities to study the project documents and respond.
Correct Answer: C [Alembic Pharmaceuticals (2020)]
Explanation:
In Alembic Pharmaceuticals v. Rohit Prajapati (2020), the Supreme Court held ex post facto EC to be contrary to environmental law.
Correct Answer: B [Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013]
Explanation:
The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 requires a social impact assessment (SIA), with Gram Sabha consultation, before land is acquired for most public purposes. The SIA studies effects on affected families, livelihoods and public facilities, unlike an EIA, which studies environmental effects.
Correct Answer: B [10 km]
Explanation:
Under the General Condition of the EIA Notification, 2006, a Category B project located within 10 km of a protected area, critically polluted area, eco-sensitive area, or an inter-State or international boundary is treated as Category A. It is then appraised at the Central level by the Expert Appraisal Committee of MoEFCC.
Correct Answer: C [2-1-3-4]
Explanation:
The USA enacted NEPA in 1969, India issued its first EIA Notification in 1994, replaced it with the 2006 notification, and released the Draft EIA Notification for comments in 2020. So the order is 2-1-3-4.
Correct Answer: A [conveying a false impression that products are eco-friendly]
Explanation:
Greenwashing is creating a false impression that a company or its products are eco-friendly and environmentally sound, usually through misleading advertising or labels. It has nothing to do with detergents, waste-water treatment or roadside planting; the term borrows from 'whitewashing' (covering up).
Correct Answer: B [1 and 2 only]
Explanation:
Statements 1 and 2 are correct: SEBI mandates the Business Responsibility and Sustainability Report for the top 1,000 listed companies by market capitalisation, and its ESG disclosures are largely non-financial. Statement 3 is wrong because the RBI has no role in mandating BRSR.
Correct Answer: A [Expert Appraisal Committee of the MoEFCC]
Explanation:
Under the EIA Notification, 2006, Category A projects are appraised by the Expert Appraisal Committee (EAC) of MoEFCC and receive environmental clearance from the Central Government. Category B projects, in contrast, are appraised by the State Expert Appraisal Committee and cleared by the State Environment Impact Assessment Authority.
Correct Answer: B [II only]
Explanation:
Statement I is wrong because the Business Responsibility and Sustainability Report (BRSR) is mandated by SEBI, not the RBI, and only for the top 1,000 listed companies by market capitalisation, not all listed companies. Statement II is correct, since BRSR disclosures on environmental, social and governance (ESG) matters are largely non-financial.
Correct Answer: A [Conveying a false impression that a company's products are eco-friendly and environmentally sound]
Explanation:
Greenwashing means conveying a false or misleading impression that a company's products or activities are eco-friendly and environmentally sound. It is a marketing practice that exaggerates green credentials, which regulators now try to curb through disclosure and advertising rules.
Correct Answer: A [assessing the carbon footprint of building operations around the world]
Explanation:
The Common Carbon Metric was developed by UNEP's Sustainable Buildings and Climate Initiative (UNEP-SBCI) to measure and report the energy use and carbon footprint of building operations in a uniform way worldwide. It helps compare buildings across countries, since buildings account for a large share of global energy-related emissions.
Correct Answer: A [long-term damage done by a tonne of CO2 emissions in a given year.]
Explanation:
The social cost of carbon is a monetary estimate of the long-term damage (to health, agriculture, property, ecosystems) caused by emitting one additional tonne of CO2 in a given year. Governments use it in cost-benefit analysis to value the benefit of policies that cut emissions.
Correct Answer: A [It is an international accounting tool for government and business leaders to understand, quantify and manage greenhouse gas emissions.]
Explanation:
The GHG Protocol, from WRI and WBCSD, is the standard accounting tool for governments and businesses to quantify and manage emissions.
➤ Full notes, maps, tables, a reason for every option and Mains PYQs – U18 · Environment and Ecology (UPSC book, ₹249): www.shanmugamiasacademy.in/study-materials/upsc-environment-ecology
Today Current Affairs in Tamil | 23 நவம்பர் 2026 | TNPSC Group 4 முக்கிய வினாக்கள்
📚 TNPSC குரூப் 4 / 2 / 2A – பொதுத்தமிழ், பொது அறிவு நூல்கள்
PDF நூல்கள் · ₹149 முதல் · ஒவ்வொன்றுக்கும் 50 பக்க இலவச மாதிரி · UPI-இல் பணம் செலுத்தியதும் உடனே பதிவிறக்கம்
பொதுத் தமிழ் — முழுமையான கையேடு (TNPSC குரூப் 2 · 2A · 4)
₹199
TNPSC முழுமையான பாடநூல்கள் – முழுத் தொகுப்பு (9 நூல்கள்)
₹1599
பொதுத் தமிழ் — முந்தைய ஆண்டு வினா – விடை – விளக்கம் (புதிய பாடத்திட்டம்)
₹199
TNPSC திறனறிவும் மனக்கணக்கு நுண்ணறிவும் (Aptitude & Mental Ability) – முழுமையான பாடநூல்
₹199TNPSC குரூப் 1, 2/2A, 4 – நேரடி வகுப்புகள் · கோவை & மதுரை
2006 முதல் சண்முகம் IAS அகாடமி · Classroom & online coaching in Coimbatore and Madurai